LTM tenders of Khulna district. |
OSTETM tenders of Khulna zilla. |
OTM tenders of Khulna. |
View All the active tenders of Khulna district.
eGP Tender ID: 897126; Works (NCT)
APP ID: 194569;
District: Khulna
Reference No.: Memo No: 1336, Date: 01/11/2023
Package Title: River bank protective work along the right bank of shakbaria river from km. 27.860 to km. 28.360 = 500m at angtihara in polder no. 14/1; upazila: koyra, district- khulna, under khulna o&m division-2, bwdb, khulna during the year 2023-24.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Khulna O&M Division-2
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2023-11-02 12:00:00
Document last selling: 2023-12-03 16:00:00
Closing / Opening: 2023-12-04 11:00:00
Brief Description of Package: Sat-2/26
River bank protective work along the right bank of shakbaria river from km. 27.860 to km. 28.360 = 500m at angtihara in polder no. 14/1; upazila: koyra, district- khulna, under khulna o&m division-2, bwdb, khulna during the year 2023-24.
Tender Document Price: Tk. 4000;
Tender Security: 8600000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 4000, estimated cost should be more than 2 crore BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 286666666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 860000000 BDT.
Thus, Official Cost Estimate should be BDT. 286666666 ~ 860000000.
Eligibility criteria:
1) All tenderer must be registered in e-gp portal system.
2) Payment will be made upon availability of fund; no claim will be entertained.
3) It is the tenderer's responsibility to submit all documents in their original form. If any documents become corrupted and the evaluation team is unable to open the file, no claim will be considered.
4) VAT & IT from bill will be deducted as per prevailing Government Rate.
5) If any type of Structure/Obstrucle is needed to dismantle to execute the work as per Design & Specification, the tenderer will do this at his own expense. No extra claims will be considered.
6) The tenderer must follow the latest instructions and formats of CPTU.
7) If BWDB owned land is not sufficient to execute the work as per design & Specification, the bidder will do this at his own expense and planning.
8) It is mandatory to submit video and still photographs of the said work in pre-work and post work condition to PE at contractor's own cost.
9) Quantity of work may extremely change and Design may also be modified.
10) Cost of pre work, interim and post-work survey will be borne by the contractor.
11) The work must be executed as per approved design uploaded at Sec-9 & technical specifications of BWDB uploaded at Sec-7of tender document.
12) The approved taskforce guideline uploaded at Sec-8 will be followed.
Project: Rehabilitation of Polder no.14/1 in Khulna District
Location of work / delivery: Koyra Khulna
Budget Type: Development
Category: Construction work for water projects; Works for complete or part construction and civil engineering work;
PE Address: 13, Gagan Babu Road, Khulna, City: Khulna, Thana: Khulna City Corporation, District: Khulna - 9000, Country: Bangladesh,
See more tenders from
Khulna O&M Division-2; Bangladesh Water Development Board (BWDB):
1002486 : KHU2/NDR 2024-25/01
Supply of 175 kg wt empty polyestar geo- textile bag with necessary arrangement of filling & placing/dumping to meet up emergency condition during flood under operation and maintenance budget Under Khulna O&M Division-2, BWDB, Khulna, FY-2024-2025.
987401 : Khu2/14-1/2023-24/10
Supply of Engineering Instrument (Total Station-1no & Echosounder-1no) in Connection with "Rehabilitation of Polder No- 14/1 in Khulna District" Under Khulna O&M Division-2, BWDB, Khulna During the Year 2023-2024.
959676 : Sat-2/44
Repair of existing protective work along the right bank of shakbaria river from km. 26.910 to km. 27.860 = 950m in polder no. 14/1; upazila: Koyra, district- Khulna, under Khulna O&M Division-2, BWDB, Khulna during the year 2023-24.
957456 : 03/2021-2022/DRMEP/S-2
Precautionary Re-sectioning work of embankment along with slope & bank protection work in between km. 12.650 to km. 15.200= 2550.00meter at Modinabad total length= 2550.00 meter in polder no 13-14/2, Upazila- Koyra, District- Khulna in C/W "Disaster Risk Management Enhancement Project (Component-3)" under Khulna O&M Division-2, BWDB, Khulna.
957455 : 02/2021-2022/DRMEP/S-2
Precautionary Re-sectioning work of embankment along with slope & bank protection work in between km. 9.500 to km. 12.650= 2400.00meter at Gobra total length= 2400.00 meter in polder no 13-14/2, Upazila- Koyra, District- Khulna in C/W "Disaster Risk Management Enhancement Project (Component-3)" under Khulna O&M Division-2, BWDB, Khulna.
957454 : 01/2021-2022/DRMEP/S-2
Precautionary Re-sectioning work of embankment along with slope & bank protection work from (1) km. 75.500 to km. 76.100= 600.00meter at Motbaria, (2) km. 88.350 to km. 88.500= 150.00meter at Rotna, (3) km. 91.000 to km. 91.770= 770.00meter at Shakbaria, total length= 1520.00 meter in polder no 13-14/2, Upazila- Koyra, District- Khulna in C/W "Disaster Risk Management Enhancement Project (Component-3)" under Khulna O&M Division-2, BWDB, Khulna.