eGP Tender ID: 936841; Works (NCT)
APP ID: 197228;
District: Tangail
Reference No.: T-06/2242; Date: 12/01/2024
Package Title: repair/re-sectioning of embankment from km 7.530 to km 7.620 = 90.00 m along the left bank of Jhenai River at Bolibodrow Union in c/w "Jopna-Kariyata FCD project" in Dhanbari Upazila of Tangail District under Non-Development Revenue Budget under Tangail WD Division, BWDB, Tangail during the year 2023-24.
Organization: Bangladesh Water Development Board (BWDB)
Procuring Entity: Tangail WD Division
Procurement Method: Open Tendering Method (OTM)
IFT Published on: 2024-01-14 17:00:00
Document last selling: 2024-01-29 17:00:00
Closing / Opening: 2024-01-30 11:40:00
Brief Description of Package: repair/re-sectioning of embankment from km 7.530 to km 7.620 = 90.00 m along the left bank of Jhenai River at Bolibodrow Union in c/w "Jopna-Kariyata FCD project" in Dhanbari Upazila of Tangail District under Non-Development Revenue Budget under Tangail WD Division, BWDB, Tangail during the year 2023-24.
Tender Document Price: Tk. 1000;
Tender Security: 65000 BDT
Official Cost Estimate (Prediction):
* Since document price is Tk. 1000, estimated cost should be less than or equal 50 lacs BDT.
* Tender Security can be maximum 3% of Official Cost Estimate. So estimated cost is more than Tk. 2166666.
* Tender Security is normally more than 1% of Official Cost Estimate. So estimated cost should be less than 6500000 BDT.
Thus, Official Cost Estimate should be BDT. 2166666 ~ 5000000.
Eligibility criteria:
As specified in the TDS
Location of work / delivery: Dhanbari Upazila
Budget Type: Revenue
Category: Engineering works and construction works; Works for complete or part construction and civil engineering work;
PE Address: Akur Takur Para, Mymensingh Road, City: Tangail, Thana: Tangail Sadar, District: Tangail - 1900, Country: Bangladesh,
See more tenders from
Tangail WD Division; Bangladesh Water Development Board (BWDB):
1060757 : NDR/Tangail/Boro Basalia/W-46/2024-25
Precautionary Temporary protective work along the left bank of Pongli River from Km 0.00 to Km 0.037 = 37.00 m to protect school Feild from the Pongli River erosion at Boro-Basalia in UP. Mogra, UZ. Tangail Sadar, Dist. Tangail under Tangail WD Division, BWDB, Tangail during FY 2024-2025.
1060756 : NDR/Tangail/Salina/W-45/2024-25
Precautionary protective work along the right bank of Pungli river to protect the Embankment of Compartmentalization Pilot Project (CPP) from KM 29.780 to KM 29.834 = 54.00 m at Salina in Union: Gala, upazilla: Tangail Sadar, District: Tangail under Tangail WD Division, BWDB, Tangail during the FY 2024-2025.
1060755 : NDR-Tangail/Rana Gasa/W-44/2024-25
Precautionary protective work along the right bank of Pungli river to protect the Embankment of Compartmentalization Pilot Project (CPP) from Km. 35.200 to Km. 35.237 = 37.00 m at Rana Gasa in Union : Garinda, upazilla: Tangail Sadar, District: Tangail under Tangail WD Division, BWDB, Tangail during the FY 2024-2025.
1060753 : NDR/Tangail/Warshi/W-43/2024-25
Precautionary protective work from Km 0.111 to km 0.150=39m along the Right bank of Dhaleshwari river at Warshi Paik Para M. Yasin & Younus Khan High School adjanct area of Warshi union in Mirzapur Upazila District: Tangail under NDR Budget under Tangail WD Division, BWDB, Tangail, during the year 2024-25.
1060752 : NDR/Tangail/Suruz/W-42/2024-25
Re-sectioning and Re-construction of embankment of Compartmentalization Pilot Project (CPP) from km 34.400 to km 34.500 = 100.00m in C/W NDR Budget of Tangail WD Division, BWDB, Tangail during the FY 2024-2025.
1060750 : NDR/Tangail/Akua Bazar/W-41/2024-25
Precautionary protective works to protect the embankment, homestead, educational & religious institutions from left bank erosion of Pungli river from km. 4.108 to km. 4.150 = 42.00m at Akuabazar in Kalihati upazila of Tangail district under Tangail WD Division, BWDB, Tangail during the year 2024-25.